As we wrap up the 6th week of demolition, we’re excited to share that the Wheeling Inn has been fully demolished, leaving behind only large piles of debris. While this marks a significant milestone, much work remains, particularly in sorting and processing the rubble. In earlier updates, it was communicated that there were plans to transport debris off-site for processing. However, after careful evaluation, project stakeholders have approved bringing a crusher to the site instead. This decision reduces traffic disruptions and enhances pedestrian safety but will result in a slight increase of noise for surrounding neighbors between 8:00 AM and 5:00 PM. Proper dust and noise mitigation measures will be in place throughout this process. The crushing process is scheduled to begin shortly after Thanksgiving and is expected to conclude before Christmas.